Managing project scope creep in construction industry
Osuva_Ajmal_Khan_Gunasekaran_Helo_2022.pdf - Hyväksytty kirjoittajan käsikirjoitus - 827.22 KB
Pysyvä osoite
Kuvaus
©2022 Emerald Publishing Limited. This manuscript version is made available under the Creative Commons Attribution–NonCommercial 4.0 International (CC BY–NC 4.0) license, https://creativecommons.org/licenses/by-nc/4.0/
Purpose
Project scope creep is a nightmare and nearly intolerable task. Most project managers struggle to curtail the expanse and degree of scope creep. This study examines different likely project scope creep factors associated with the construction industry projects.
Design/methodology/approach
After many brainstorming sessions with construction stakeholders, several project scope creep factors were identified. Then, a detailed survey was executed in big construction projects of the United Arab Emirates (UAE). The data were analyzed using exploratory factor analysis (EFA) and confirmatory factor analysis (CFA).
Findings
The results derived and validated five conspicuous factors leading to project scope creep. Respectively, the highest and the lowest impact on project scope appears to be imposed by tasks/specifications and complexity/uncertainty.
Practical implications
It offers crucial support to the project stakeholders in scrutinizing different factors that stand as hurdles to project success and allows them to seek remedies to resolve them.
Originality/value
It is among the first study in the region that identifies and validates the factors that hinder construction project success.
Emojulkaisu
ISBN
ISSN
1365-232X
0969-9988
0969-9988
Aihealue
Kausijulkaisu
Engineering, Construction and Architectural Management|29
OKM-julkaisutyyppi
A1 Alkuperäisartikkeli tieteellisessä aikakauslehdessä